06. Engineering Work Overview

엔지니어링

by oksk
이 글은 브런치북 "화공플랜트 EPC 엔지니어링"을 아마존에 출간하기 위하여 AI 도움을 받아 영문으로 번역한 내용입니다. 보완한 원문을 한글 서적으로도 출간하기 위해 영어 번역본 아래에 함께 올립니다.


ENGINEERING?


Even after working in engineering for 35 years, I still find it difficult to give a clear answer when someone asks me, “What exactly is engineering?”.

It is a word I use almost every day, yet when pressed for a precise definition, I hesitate. I have searched in many places for a clear definition, but I have not yet found one. Perhaps this is because the term is used so broadly that it is difficult to capture its meaning in a single sentence. In fact, what matters more than the definition itself is understanding how engineering is actually carried out in practice.


Although it is not a strict definition, I would like to introduce a description that explains quite well how engineering is conducted in the plant industry.


An Oil & Gas facility project is usually developed in 4(four) steps.

Mr. Hervé Baron, in his book The Oil & Gas Engineering Guide, divides the development of an Oil & Gas project into four stages and explains them as follows:


1. The business planning phase,

Objective : Define the Business opportunity

Content :Technical assessment, milestone schedule, estimated cost range

Deliverables : Functional requirements, economic evaluation

By : Plant Owner




**The rest of this chapter is omitted for the final publication.**





엔지니어링?

35년을 엔지니어링 업무에 종사했지만, 주변에서 엔지니어링이 무엇이냐는 질문을 받으면 아직도 '엔지니어링이란 이런 것이다'라고 딱히 답을 하지 못합니다. 늘 입에 붙어 있는 말이면서도 그렇습니다. 명확한 정의를 알기 위해 이곳저곳 찾아보았지만 아직까지 찾지 못했습니다. 하긴 워낙 광범위하게 사용되는 단어이다 보니 오히려 명확한 정의를 내리기가 어려운 것 같다는 생각이 들기도 합니다. 사실 용어의 정의보다는 실제 어떻게 진행되는지를 아는 것이 더 중요하겠지요. 엔지니어링의 정의는 아니지만, 플랜트 산업에서 엔지니어링이 어떻게 진행되는지 비교적 잘 설명된 내용이 있어 소개하고자 합니다.


Mr. Herve Baron은 그의 저서 'The Oil & Gas Engineering Guide에서 Oil & Gas Project'의 에서 엔지니어링을 4 단계로 구분하고 다음과 같이 설명하고 있습니다.


An Oil & Gas facility project is usually developed in 4 steps.


1. The business planning phase,

Objective : Define the Business opportunity

Content :Technical assessment, milestone schedule, estimated cost range

Deliverables : Functional requirements, economic evaluation

By : Plant Owner


2. The conceptual design, also called Basic Engineering phase,

Objective : Confirm feasibility, select technology, refine cost estimate, identify risks

Content : Evaluate alternates, confirm feasibility, develop process design

Deliverables : +/- 30% cost estimate, preliminary schedule, layout, process design

By : Engineering Company


3. The Front End Engineering Design (FEED) Stage,

Objective : Refine cost estimate, prepare EPC phase

Content : Evaluate alternates, confirm feasibility, develop process design

Deliverables : +/- 10% cost estimate, Design basis for EPC, Material Requisitions for Long Lead Items

By : Engineering Company


4. The facility Detailed Engineering and Construction


이해하기 쉽게 잘 정리한 것 같습니다. 이 중에서 3단계까지는 발주처에서 수행하고 마지막 4단계인 Detailed Engineering과 Construction Engineering만 EPC Contractor가 수행하는 것이 일반적입니다. 따라서, 여기서는 Detailed Engineering와 Construction Engineering에 대해서만 자세히 살펴볼 예정입니다.




대한민국 플랜트 산업의 부흥을 꿈꾸는 자, oksk